Passa al contenuto
Menu
È necessario essere registrati per interagire con la community.
La domanda è stata contrassegnata
1 Rispondi
2077 Visualizzazioni

Hi all

In Odoo 14 enterprise. Is it possible to calculate product process cost from the manual entered planned process time instead of the actual process time?


Regards,
Rickard

Avatar
Abbandona
Autore Risposta migliore

Ok so I found out how it works.

In product.product there is a smart button "Cost Analysis". This functionality is calculationg actual cost of: BoM+operations+scrap. However, in mrp.bom there is a another smart button "Structure & Cost". This one is calculation cost of: Bom+planned operation. The latter is also the one used for product cost and inventory valuation.

Hence, my problem wasn't really a problem :)

Avatar
Abbandona
Post correlati Risposte Visualizzazioni Attività
1
feb 25
3769
1
dic 24
1064
3
ott 23
2456
3
apr 23
2279
0
gen 22
1263