Skip to Content
Menu
You need to be registered to interact with the community.
This question has been flagged
1 Odgovori
2059 Prikazi

Hi all

In Odoo 14 enterprise. Is it possible to calculate product process cost from the manual entered planned process time instead of the actual process time?


Regards,
Rickard

Avatar
Opusti
Avtor Best Answer

Ok so I found out how it works.

In product.product there is a smart button "Cost Analysis". This functionality is calculationg actual cost of: BoM+operations+scrap. However, in mrp.bom there is a another smart button "Structure & Cost". This one is calculation cost of: Bom+planned operation. The latter is also the one used for product cost and inventory valuation.

Hence, my problem wasn't really a problem :)

Avatar
Opusti
Related Posts Odgovori Prikazi Aktivnost
1
feb. 25
3767
1
dec. 24
1061
3
okt. 23
2455
3
apr. 23
2278
0
jan. 22
1263