I was trying to add 90 days to a date field:

for record in self:
record['x_studio_90_days'] = record.x_studio_det_days + datetime.timedelta(days=90)

however I am getting an error. Please help

Avatar
Abbandona
Risposta migliore

Hi Neil,

Check this forum post: https://www.odoo.com/forum/help-1/how-to-add-42-days-to-an-date-field-108946

Thank you

Avatar
Abbandona
Autore

I have tried that one but it gives me a lot of errors

Hi,
Try this:
if record.x_studio_det_days:

record['x_studio_90_days'] = record.x_studio_det_days + datetime.timedelta(days=90)

Thank you

Risposta migliore

Hi  Neil Matan,

Try,

from dateutil.relativedelta import relativedelta

self.event_start = fields.Date.today() + relativedelta(days=7)


Avatar
Abbandona

record['x_studio_90_days'] = record.x_studio_det_days + relativedelta(days=90)