Hello there :)

To be honest, I get a little confused, wenn it comes to lead times and dates. In general we set every thing to 0 days. 

When I confirm a sales order, the planned date of the manufacturing orders are in the past, set to last monday, to be more precise. 

Can anyone tell me why? I am using Odoo 14 E, btw.