I see in the demo site that each task has a start and end plan date. In my own database, I can set a start/end for the entire project but not for each individual task. Can anyone tell me how to turn this feature on?

الصورة الرمزية
إهمال

please tell me about odoo version in your local machine?

الكاتب

Sure, I'm trying out the latest 16 from the repo. We are pretty keen to use project and being able to set up the start and end dates from the form view is pretty important.

الكاتب

To clarify, I should have said the latest from Git.

أفضل إجابة

I am trying to see in 16 version but i not found it, but i already found it in version 15, you can install version 15 you will find it, and you should configuration Planning from: project -> configuration -> Setting ->Time Management: planning

الصورة الرمزية
إهمال
الكاتب

Yes, that is selected on 16. Going back to 15 means we would also loose the new features. I believe this will become a major inconvenience for people using 16.

أفضل إجابة

I have the exact same problem in 16. It only appears, once you have planned it in the Gantt view. Which is very inconvenient

الصورة الرمزية
إهمال
الكاتب

After reading lots of posts, I wrote this module to fix it:
https://github.com/mpiko/task_planning

Odoo work in strange ways indeed!!!