It is possible that the Manufactoring order produces only the number (or the multiple number) of items?

Example: Its only possible to punch 50 pcs at once. when i need 60 pcs and 5 pcs are on stock so a Manufactoring Order of 100 pcs is necassary.


形象
丢弃
最佳答案

Unfortunately I cannot answer your question because it is not very clear, but two Odoo concepts come to mind:

  • MTO
  • Reordering rules

A summary can be found here, and if you analyze the two concepts, you quite surely will find the solution for your needs!

形象
丢弃
编写者

Thx Ricardo. I tried some things but i think its always same concept: the work order prudeces the number of items are requested. I need the possibility to produce the number of items possible in the manufactoring process. for example: its only possible to pruduce 50 pcs. at once. so if i need 60 items i have to produce 100 items (2x50). in mrp its possible to consume 0.5 units (i could round it to 1, but that makes no sense).