Hello,
I have a bill of Material consisting of 2 operations, in 2 different work locations.
I would like either:
- To Assign 2 different repsonsiblesto the 2 Work Orders inside the Manufacturing Order automatically, with an automated rule
- To Assign 1 responssible of the Manufacturing Order that is then updated when the 1st Work Order is complete.
I tried the 1st option but I only managed to assign responsible for the first WO inside the WO.
Could you help me?
Thanks,