跳至内容
菜单
此问题已终结
1 回复
4384 查看

This workaround allows to reserve the work center for parallel operations without increasing the time reserved in the planning.

Ex : We have a work center in which we need 3 operations to run simultaneously, the total time for all the operations is 1 hour. 

With the standard configuration every operation is planned after each other:


形象
丢弃
编写者 最佳答案

The objective is to book the work center for 1 hour instead of 3 hours. By artificially increasing the efficiency of the work center to 300 % we can mimic the parallel operation run :



形象
丢弃
相关帖文 回复 查看 活动
1
3月 24
7035
0
6月 25
2998
1
2月 23
2953
1
9月 22
7521
2
1月 23
4846