Skip to Content
Menu
This question has been flagged
1 Atsakyti
4138 Rodiniai

This workaround allows to reserve the work center for parallel operations without increasing the time reserved in the planning.

Ex : We have a work center in which we need 3 operations to run simultaneously, the total time for all the operations is 1 hour. 

With the standard configuration every operation is planned after each other:


Portretas
Atmesti
Autorius Best Answer

The objective is to book the work center for 1 hour instead of 3 hours. By artificially increasing the efficiency of the work center to 300 % we can mimic the parallel operation run :



Portretas
Atmesti
Related Posts Replies Rodiniai Veikla
1
kov. 24
6700
1
vas. 23
2783
0
lapkr. 23
2659
1
rugs. 22
7239
2
saus. 23
4636