I have a task that takes up 7 workdays.

When i want to plan it, automaticly plans it from monday to a sunday...

How do i set up my database so it does not include saturdays and sundays? It only plans in work when my employees are available: monday throught friday.

Avatar
Vazgeç
En İyi Yanıt

Hello!
You should configure your resource calendar

Avatar
Vazgeç

Hello Marcelo,

Can you explain more ? I am interested.

Thank you

Did you received an answer because I"m also interested in only planning in weekdays and not the possibility to do in weekends?