We are using Project and want to set default assignees to Stages within projects. Can this be done with Automated Actions?


For example:

Stage New Order = all tasks get Bill as default assignee

Stage In Progress = all tasks get Melissa as default assignee

Stage Delivery = all tasks get Paul as default assignee

Avatar
Vazgeç
En İyi Yanıt

Component is selected, and that Component has a Component Lead and is set for Component Lead assignee, the issue is assigned to the Component Lead.

Avatar
Vazgeç
En İyi Yanıt


Avatar
Vazgeç

where can i open the form like your image?