Skip to Content
Menu
This question has been flagged
1 Odpoveď
1890 Zobrazenia

When using manufacturing in Odoo16,how does the system calculate the scheduled date and scheduled end date when clicking on the 'planned' button? I'm looking for insights into the process behind determining the scheduled date to better understand the workflow.

Avatar
Zrušiť
Best Answer

It calculate the time necessary to manufacture the planned qty from the time set in the operation in the BOM.  The time is what it take to manufacture 1 pcs. 

It will schedule the start date according to the schedule date on the manufacturing order, for the fist available time slot long enough to complete the order.  If the schedule date is in the past, it will look from today and forward.

Avatar
Zrušiť
Related Posts Replies Zobrazenia Aktivita
0
mar 25
1045
3
sep 25
278
1
sep 25
314
0
aug 25
386
2
aug 25
936