I  have 5 workcentres and each of them is doing different operations.

There  are some cases where a single workorder is required  multiple workcentre involvement as work will be distributed among them as different areas of the work are done by different workcentres.


How is it possible to handle jobs which are distributed more than multiple workcentres ?


아바타
취소
베스트 답변

You can have a single Manufacturing Order which has operations performed at different work centers. You can set-up the routing in the "Work Orders" Tab.

If this routing is always applicable for the manufactured product you can set-up while creating the BOM in the "Operations" tab

If you don't view the above options in MO and BOM, you might need to enable "Work Orders" option in Setting > Manufacturing > Operations