Our assembly process is to assemble large bolted assemblies in teams in a bay, I have the bay setup as a work centre, however this seems limited to 1 shift time (1 worker) how can I handle this type of assembly, ideally if I could put 3/4 workers in a work centre this would be perfect, am I missing something or is this not an option? 

Avatar
Buang
Penulis

Dear Sender,

 

Thank you for your email, I am out of the office with no access to emails, your message is important to me I will respond when I return on 24/07.

 

Best Regards

 

Jamie

 

Jawaban Terbai

Hello, i do not know if i can upload picture, but basically you can add responsible person for the work center(team leader for example). Inside the work center you can add operations and operation steps. In each operation step you can add responsible person.

Avatar
Buang