Hi i'm new in odoo so i hope so you can help me

i have a mean manufacturing order include 40 product to be manufacturing 

how can i do it in Manufactoring orders in simple steps ?


Avatar
Buang
Jawaban Terbai

Hi,

You can try this way

1. You need to set the BOM for each product
2. We can't able set a manufacturing order for 40 products in a single order since it is a distinct product, so we can do a reordering rule, if the product comes to a particular level, we can trigger a MO for those products

Another way we also have the master production schedule for which it is scheduled the production ase don forecast or demand

if the production is based on order using route MTO we can replenish the required Quantity
For more reference, you can refer to this https://www.cybrosys.com/odoo/odoo-books/odoo-book-v16/manufacturing/

Hope it helps

Avatar
Buang
Jawaban Terbai

As answer by Cybrosys you can only have one product to produce in a manufactiriog order.  But it is possible to mass confirm manufacturing orders from the list view:

- If you do not use work center / work orders

- If you it is OK to confirm consumption of components without variations. Equal to what is set in the BOM.

Avatar