In my v7.0 environment, when I record the time through Human Resources -> My Current Timesheet choosing an analytic account, analytic journal items are generated but with no costs (even though I have assigned a service item with cost price to the employee), while it does recognize costs when I enter the time through Projects -> Timesheets. Why are the behaviors different?

Avatar
Buang

I guess it needs to be approved in my current timesheet. This is not the case in Timesheet Activities.

Penulis Jawaban Terbai

Just found out that the cost is recognized in analytic account for the hours input via My Current Timesheet function (even before approval) in Version 7.0-20130717-231254. I guess there was a bug in older version.