Hello,
The gantt chart is hard coded in the Odoo 8 saas and it doesn't take into account the specified working hours of the working centers.
If a working center works 14 hours a day (2 shifts) and if it needs in the reality only one day to accomplish a 14 hours task, the gantt will display 2 full days, as it considers, that the company works in one shift 8 hours per day.
I have installed Odoo 8 on Ubuntu Server and would like to hard code the gantt and let it work with 14 hours per day.
As I am not a technical guy, could any one tell me how to accomplish that? That would be really great, because for a manufaturing company as ours, it is absolute impossible to work without the gantt chart.
Thank you.