This question has been flagged

Hi!

When we start the procurement manually (Version 7), the dates of all quotations are set to today.

But what we want is, to set the date to "start of production - delivery time - security days".

We don't want to fill our warehouse in next days (today + delivery time), when the production of the product is going to start in a year ...

Is it a bug or what are we doing wrong?

Thanks!