Skip to Content
Menu
This question has been flagged

Currently in Odoo, we can setup 2 step picking for receipts, delivery, and manufacturing, but not for the subcontracting route. 

Avatar
Discard
Author Best Answer

1. Activate the subcontracting route on the Manufacturing module.

2. Go to the Inventory module > Configuration > Operation Type

3. Create a new operation, with the type Internal Transfer, and set the source location to be the picking location, and destination location to be the output location:



4. Go to the Inventory module > Configuration > Routes > Resupply Subcontractor


5. Change the current rule to the following configuration:




6. Create a new rule with the following configuration:


Make sure to set the two rules on the following order:

 

Now, when the user creates the PO for the trigger the subcontracting process, there will be a picking operation before the delivery:




Avatar
Discard
Related Posts Replies Views Activity
1
Jun 21
3627
3
Mar 25
20316
2
May 21
10327
1
Feb 22
3950
1
Aug 24
4448