Ir al contenido
Menú
Se marcó esta pregunta
1 Responder
7463 Vistas

Non of the automated repeating actions in the server is performed automatically:

- fetchmail, mail queue, garbage collect,...The schueduled time for the start lies in the past (3days) and does not move.

Checked that the server is in UTC Time: configured it in GMT+2 so its the correct time zone for the server. At installation time the UTC-hardware-clock was enabled in the virtual machine. that was different from my previous installations. could that have caused the inactivity of the schueduler now?

Server is running in openerp-gevent mode. Could that cause it?

I also tried the actualisation of the base module. This was also recomended in another disussion.

Did check all the ideas from here: https://www.odoo.com/forum/Help-1/question/Scheduler-not-working-21748

Ideas how to fix the schueduler?

Thank You.

Avatar
Descartar
Autor Mejor respuesta

I did not stop searching: Here is the answer: 

gevent is stopping the cron jobs!

https://openerp.my.openerp.com/nl_NL/forum/Help-1/question/Live-Chat-Running-with-Gevent-and-Cron-stops-working-34171

Avatar
Descartar
Publicaciones relacionadas Respuestas Vistas Actividad
1
mar 24
2062
0
nov 17
3792
1
ene 16
3983
1
mar 15
9023
2
mar 15
6367