Zum Inhalt springen
Menü
Sie müssen registriert sein, um mit der Community zu interagieren.
Diese Frage wurde gekennzeichnet
1 Antworten
1398 Ansichten

Hey,

When I create a sub task normaly it is not visible in the project overview but only in the list of the task it is the sub-task for. So far so good.

But as the title says the automatically generated tasks and subtasks are all shown in the project overview in the very first (left) phase.

When multiple tasks with multiple sub-tasks are being generated, then the whole project overview is a mess. Is that indended? I thought the sub-task feature is exactly for that - keeping the project's kanban overview clean and tidy.


Avatar
Verwerfen
Autor Beste Antwort

After some comparing I noticed that - unlike the normally created sub-tasks - the automatically generated sub-tasks do have the field "project" filled out with the projects name and when I remove it from there, it is not visible on the overview (as intended/expected) anymore.


Is there a way to disable this field to be filled upon generation?

Avatar
Verwerfen
Verknüpfte Beiträge Antworten Ansichten Aktivität
1
März 24
1816
0
Feb. 24
1589
2
Okt. 23
1757
3
Sept. 23
2603
1
Juli 23
1968