Hi ! I've a question about MRP. Let me explain how we operate. We produce product, and during the process of fabrication we have to send subproduct to a subcontractor, and this subcontractor will return us the new product. How can I use MRP and BoM to add this step?

thx !

John.

아바타
취소
베스트 답변

You need to create a supplier location and then add it as a routing to the BOM of the product in question.

Configuring a Location

  • Location Type: Supplier Location
  • Address: Select the address of the
  • supplier Chained location type: Fixed
  • Chained location if fixed: Your Stock
  • Lead time: No. of days for return of goods

To bill for the service add a product of type service to the BOM!

This link outlines the process http://doc.openerp.com/v6.1/book/5/5_15_Manufacturing/5_15_Manufacturing_forecasting.html#working-with-subcontractors

아바타
취소

The answer is too old and seems not relevant and not used for the current version 9, 10 and 11.

작성자 베스트 답변

Thanks Nikolaj. And how can I forbid production while my sub-products are not in stock?

아바타
취소

That would depend on the configuration of the sub-product. If it is type make to stock and minimum order rules are in place the system should generate a PO for them. In any case the moves are only completed when you 'Produce', so the system will not automatically assume you have sent to and received from the subcontractor.

I have not yet fully evaluated sub-contracting yet for myself, but have a mess around with it, it is reasonably straight forward!

베스트 답변

Hello,

You can see the comment#11 of lp:1025140. Will helps for subcontracting configuration.