I am testing warehouse's reordering rules to get familiar with them.

I set a rule in which the minimum quantity of Product1 is 5 (and max = 10).

I manufacture 1 product in which Product1 is in the bill of materials.

Since before production the on hand quantity of Product1 is 5, after production it becomes 4 (under min value).

I run schedulers and i expect something to happen, but if i go to purchases i see nothing in Request or Quotation or Purchase Orfers.

Could you please give me an hint?

Thank you.

アバター
破棄
著作者

I forgot to mention that i defined a supplier for product1

著作者 最善の回答

I need to reply my own question. After commenting the question i double checked and i realized Prouduct1 did not have a supplier defined in the "Procurements" tab, I set the supplier in a product with a similar name.

So now if i run schedulers after this I see a new "Request for Quotation", so the issue was the missing supplier in the product procurements.